The Plan:
- As Don stated: “All I have to say is make sure you get a backup after the QOH load and before loading the PO’s in case there is any problem with the PO’s.”
- Continue on with the POLINES conversion as scheduled at 2:00 AM.
- Once done, post the quantity on hand. Speaking to Don about your approach, we are using 4 hours as the estimated duration for posting. This takes us to 9:00 AM from what we can see.
- If all goes well (we will know more around 7:00 AM) we should have the Member Quote extracts for you around 10:30 AM. If this is the case, we will be running only an hour and a half behind schedule. (Do not quote me though.) I will indicate to the others that the estimated delay at this moment is 2 hours with a more accurate estimate scheduled for 7:00 AM.